Tying into a Baseline
In this method you tie buildings sides or estate bounderies into a baseline.This method can be used when you measure in a given frame
(estate bounderies) or created grid (baselines).
Advantages: This method is only used in connection with other surveying procedures, mostly with the orthogonal method (chain offset). An independent surveying measure is not tolerable. A further calculation of areas is possible only with help of map distances. Disadvantages: Simple distance measuring instruments are utilisable. With an existing frame you can easily make a supplement surveing. |
Back
copyright by stefan robel, andré stelling, daniel pudlat, vt-99, 10.07.2000